Construction Update - November 2017
Construction activities
Work is continuing on the 42 bed residential aged care home for older people experiencing homelessness or at risk of homelessness at 118A Darlinghurst Road, Darlinghurst.
Works recently completed
The car wash has been demolished and the site fenced off.
Current site works
Approval from the Heritage Council has been received and the Construction Certificate for the first phase of the works has been issued.
The archaeological works commenced early this month under the close supervision of expert archaeologists and should be finalised by mid-December.
Once we obtain clearance from the archaeologist, we will commence the site remediation and excavation works which will conclude around March/April 2018.
Work will pause just prior to Christmas and recommence in early January.
Our builders are working closely with the church, particularly regarding funerals and weddings so that our operations have minimal impact.
Contact Us
For more updates of HammondCare Darlinghurst please:
Call us on 1300 426 666 or email This email address is being protected from spambots. You need JavaScript enabled to view it..
For any media enquiries, please contact HammondCare Media on This email address is being protected from spambots. You need JavaScript enabled to view it..